CIVIL ESTIMATING AND COSTING II

UNIT IV

4.1 TAKING OFF QUANTITIES OF P.H. ENGINEERING STRUCTURES
USING TRADE SYSTEM
PREPARING DETAILED ESTIMATE USING TRADE SYSTEM AND TAKE OFF
QUANTITIES FOR ALL ITEMS OF WORKS IN THE FOLLOWING P.H.
ENGINEERING STRUCTURES:
1 SEPTIC TANKS WITH DISPERSION TRENCH /SOAK PIT
2 OPEN WELL WITH MASONRY STEINING
4 SQUARE RCC OVER HEAD TANK ON FOUR COLUMNS WITH STAGING5
5.1 TAKING OFF QUANTITIES OF ROAD /BRIDGE STRUCTURES USING
TRADE SYSTEM AND IRRIGATION WORKS
PREPARING DETAILED ESTIMATE USING TRADE SYSTEM AND TAKE OFF
QUANTITIES FOR ALL ITEMS OF WORKS IN THE FOLLOWING ROAD
/BRIDGE STRUCTURES:
1 WATER BOUND MACADAM ROAD
2 CEMENT
3 CONCRETE ROAD WITH SIDE DRAINS
4 SINGLE SPAN SLAB CULVERT
5 TEE BEAM BRIDGE ESTIMATION OF IRRIGATION WORKS – AQUEDUCT,
SYPHON, FALL, ESTIMATE OF RETAINING WALLS CULVERTS.